DOC ID · MDB-KB-008REV. AUPDATED · 21 July 2026READ TIME · 10 MIN

Weld Maps & Weld Registers

The two documents that make every weld on a fabricated item traceable — what each one is, what a reviewer expects to find in them, and how they tie welders, procedures and NDT reports together in the Manufacturing Record Book.

DIRECT ANSWER

A weld map is a drawing on which every weld joint carries a unique number. A weld register (weld log) is the table behind it: one row per weld number listing the welder, the WPS, filler batch, date, NDT reports and acceptance status. Together they prove that every joint was made by a qualified welder, to a qualified procedure, and examined with the required NDT — the core of weld traceability in an MRB or MDB.

SECTION · 01

Why weld traceability exists

When a pressure vessel, pipe spool or steel structure fails, the first questions are always the same: which weld, who made it, to which procedure, and what did the NDT say? Weld traceability exists so those questions can be answered years after handover, from the documentation alone. The codes formalise it, but the driver is practical: without a numbering system, "the weld near the nozzle" is not an auditable statement.

The industry solved this with a pair of documents that mirror each other: a marked-up drawing (the weld map) and a table (the weld register). Everything else in the welding chapter of a data book — the WPS, PQR and WPQ records, the NDT reports, the filler material certificates — hangs off the weld numbers these two documents define.

SECTION · 02

The weld map — the graphical half

The weld map is usually a copy of the general arrangement drawing, detail drawing or isometric, with a numbered balloon at every weld joint. The numbering scheme is agreed before fabrication starts: sequential per drawing, per line number, or per assembly — what matters is that every physical joint has exactly one identifier, and that repairs and re-welds get traceable suffixes (W-014-R1) rather than new numbers.

Shop welds and field welds are distinguished (typically SW/FW prefixes), and on piping work the map often lives on the isometric itself. The map answers the spatial question a table cannot: where is weld 14, and what does it join?

SECTION · 03

The weld register — the tabular half

The weld register — also called weld log, weld summary or weld history sheet — is the database view. One row per weld number. It is a living document during fabrication: rows are created when joints are fit up, welder stamps are recorded as beads go down, and NDT columns fill in as reports come back. At handover it freezes into the version that enters the MRB.

Because it accumulates gradually, the register is where traceability usually breaks. A welder ID recorded nowhere, an NDT report number never filled in, a repair executed but not logged — each is invisible in the shop and glaring at review. Keeping the register current, not reconstructing it afterwards, is the single best predictor of a clean data book review.

SECTION · 04

What a good register contains

ColumnLinks to
Weld number + drawing ref.The weld map balloon
Joint type, size, base materials + heat numbersMaterial certificates (EN 10204 MTRs)
WPS referenceThe qualified WPS and its supporting PQR
Welder ID / stampThe welder's WPQ certificate
Filler metal class + batchConsumable certificates
Welding date · repair refs (R1, R2…)Repair procedure and re-NDT
NDT methods + report numbersThe RT/UT/PT/MT reports
Acceptance status + QC sign-offFinal inspection records

Every column is a pointer into another chapter of the data book. That is the register's real function: it is the index of the welding chapter, the place where a reviewer starts every spot check.

SECTION · 05

The traceability chain per joint

Read one register row from left to right and you walk the full chain of custody for that joint: the base materials trace back via heat numbers to EN 10204 material certificates; the WPS traces to its PQR; the welder stamp traces to a WPQ valid on the welding date; the filler batch traces to a consumable certificate; and the NDT report numbers trace to signed reports with matching acceptance criteria. Five independent document trails, all converging on one weld number.

This is why reviewers love spot checks: verifying one weld end-to-end tests the integrity of the entire documentation system. If weld 14 checks out — and weld 41, picked at random, does too — confidence in the remaining hundreds rises sharply.

SECTION · 06

What the codes require

EN 1090-2 ties weld traceability to execution class: EXC3 and EXC4 require records identifying welder, procedure and location per weld; many project specs pull the same requirement down to EXC2. ASME BPVC (VIII, B31.3) requires the manufacturer to maintain welder and procedure traceability per joint — the map/register pair is the industry's standard way to demonstrate it. NORSOK and most oil & gas operator specifications require weld maps explicitly, and PED 2014/68/EU conformity assessment leans on the same records to prove qualified personnel and procedures were used.

The practical rule: assume the map and register are required, agree their format at kick-off (ideally in the ITP), and never let them lag fabrication.

SECTION · 07

What reviewers reject

  • Map ↔ register mismatches — numbers on the drawing missing from the table, or rows without a balloon.
  • Broken NDT cross-references — report numbers that don't exist, or reports covering weld numbers the register doesn't mention.
  • Welder not qualified on the date — a stamp whose WPQ expired or didn't cover the process/position.
  • Unlogged repairs — an RT report showing a repair excavation with no R1 entry in the register.
  • Illegible scans — a hand-kept register photocopied to the point of uselessness.

All five are cross-reference failures, not welding failures. The welds may be perfect; the book still bounces. See the complete MRB checklist for how the welding chapter sits among the others.

SECTION · 08

Weld maps in the MRB

In the assembled Manufacturing Data Book, the welding chapter conventionally opens with the weld map, followed by the weld register, then the WPSs, PQRs and WPQs it references. NDT reports usually live in their own chapter, reachable via the register's report numbers. Compiled digitally, those references can become actual links — a reviewer clicks from register row to NDT report instead of leafing through binders — which is precisely the kind of cross-referencing a purpose-built platform automates.

PRACTICAL APPLICATION

Click from register row to NDT report — no binders.

The MDB Builder by BizzBit launches in Q3 2026. Join the waitlist for free early access.

SECTION · 09

Frequently asked questions

What is a weld map?

A weld map is a drawing — usually a copy of the fabrication drawing or isometric — on which every weld joint is given a unique number. It is the visual half of weld traceability: it shows where each numbered weld physically sits on the item. Paired with the weld register (the tabular half), it lets a reviewer point at any weld on the drawing and trace who welded it, to which WPS, with which filler material, and which NDT report covers it.

What is the difference between a weld map and a weld register?

They are two views of the same data set. The weld map is graphical: a drawing with weld numbers ballooned at each joint location. The weld register (also called weld log or weld summary) is tabular: one row per weld number, listing the joint type, welder ID, WPS reference, filler metal batch, welding date, NDT method and report number, and accept/reject status. Most specifications require both, and reviewers cross-check them — every number on the map must appear in the register and vice versa.

What information must a weld register contain?

A typical weld register row contains: the unique weld number, drawing/line reference, joint type and dimension, base materials with heat numbers, the WPS used, the welder's identification stamp linking to their WPQ, filler material classification and batch number, welding date, any repair references, the NDT methods applied with report numbers, and the final acceptance status. Project specifications may add PWHT references, visual inspection sign-off, or hardness test results — the agreed template in the ITP or contract governs.

Are weld maps mandatory?

It depends on the code and contract. EN 1090-2 requires weld traceability for execution classes EXC3 and EXC4 (and many projects impose it at EXC2). ASME BPVC does not use the term 'weld map' but requires traceability of welders and procedures to each joint, which in practice is delivered as a weld map plus register. NORSOK and most oil & gas company specifications require them explicitly. Even where not strictly mandatory, virtually every MRB index includes a welding chapter with a weld map — client reviewers expect it.

Who prepares the weld map and weld register?

The fabricator's welding coordinator or QC department prepares and maintains both. The weld numbering scheme is normally fixed before fabrication starts (often agreed in the ITP), welders stamp or record their ID against each joint as work proceeds, and QC updates the register as NDT results come in. On multi-supplier projects, each fabricator maintains the map for its own scope, and the document controller compiles them into the Manufacturing Record Book at handover.

How do weld maps link to NDT reports in an MRB?

Through the weld number. Each NDT report states which weld numbers it examined; the weld register lists, per weld, which NDT methods were applied and the corresponding report numbers. A reviewer checking an MRB picks a weld on the map, finds its row in the register, and expects to open the exact RT, UT, PT or MT report referenced there — with matching weld number, acceptance criteria and a signed result. Broken cross-references between map, register and NDT reports are among the most common reasons data books are rejected at review.

SHARE THIS ARTICLE

Found this useful? Help another quality manager find it too.

RELATED

Back to top

Ready to build MDBs the modern way?

Join the MDB Builder waitlist. The first 50 sign-ups receive lifetime early-access pricing.

FREE STARTER CREDITS · ±3 PROJECTS · 15 MDBS · NO CREDIT CARD

MDB Builderby BizzBit
EU-HOSTED·GDPR COMPLIANT·NO INSTALLATION·BROWSER-BASED · ENTRA ID LOGIN
© 2026 BizzBit B.V. · All rights reserved.REV. A · LAST UPDATED 13 MAY 2026